Issues Publications In The News Releases Events About Us Empire Ideas Subscribe Donate

>> Government Reform

Issues

Streamlining SEQR

How to Reform New York's "Environmental" Planning Law

by: E.J. McMahon and Michael Wright
Complete report in PDF format
December 16, 2013
 

EXECUTIVE SUMMARY

 

Major residential, commercial and industrial developments throughout the country are subject to an array of federal and state laws designed to protect the environment, buttressed nearly everywhere by local land-use regulations addressing the community impacts of such projects.

 

In New York, however, these regulations are wrapped in the added red tape of the State Environmental Quality Review Act, or SEQR.

 

In this, as in so many areas of regulatory policy, the Empire State is an outlier. Less than one-third of all states have similarly comprehensive environmental review statutes —and fewer have laws as broadly applicable as New York’s SEQR. 

 

Nearly 40 years after its enactment, can SEQR be reformed to strike a better balance between environmental protection and economic growth? That’s a crucial question when much of New York, especially upstate, is suffering from what could be described as a severe development deficit.

 

Text Box: SEQR has been cited as adevelopment obstacle by several of the state’s regional economic development councils.While it would be difficult to quantify SEQR’s role in discouraging investment and job creation in New York, the added regulatory imposition certainly does little to expedite the building of new homes, businesses, factories and civic facilities. As currently written and interpreted, SEQR can be exploited to produce costly delays and uncertainty for the kind of job-creating projects New York desperately needs. Several of the state’s regional economic development councils have identified SEQR as an obstacle to development.

 

Governor Andrew Cuomo has responded to these complaints by allowing his state Department of Environmental Conservation (DEC) to float proposed rule changes designed to improve SEQR in response to years of complaints from private-sector developers. DEC says it is aiming to make the process more efficient and predictable “without sacrificing meaningful environmental review,” but the ideas it is considering don’t go far enough to achieve this goal.

 

This paper suggests that further changes are needed to truly streamline SEQR. At a minimum, the law should be revised to:

  • Reduce the potential for undue delays by imposing hard deadlines and incentives to ensure the process can be completed within a year.
  • Mandate “scoping” of environmental impacts at the first stage in the SEQR review process, but also more tightly restrict the introduction of new issues by lead agencies later in the process.
  • Eliminate the law’s reference to “community and neighborhood character” as an aspect of the broadly defined environment potentially affected by projects, since the concept already is defined by local planning and zoning laws.

 

Industry groups have proposed other, more specific changes that also deserve enactment as part of any meaningful SEQR reform process.

 

1.      ORIGINS AND BACKGROUND

 

The peak of America’s postwar economic boom in the 1960s coincided with a growing public awareness of the increasingly troubling environmental impacts of untrammelled industrial, commercial and residential development.

 

The health hazards of air pollution in major metropolitan areas had been highlighted by incidents such as a four-day temperature inversion blamed for dozens of deaths in New York City in 1965. Water pollution was also a serious problem; in the nation’s industrial heartland, portions of the Great Lakes were literally dying— becoming uninhabitable by fish or plant life. Stretches of storied major waterways such as the Hudson River had become seriously polluted. During the same period, perceived assaults on the built environment of neighborhoods and communities had led to a grassroots backlash against major highway expansion projects in some cities.

 

These concerns led to the enactment of the National Environmental Policy Act (NEPA), signed by President Richard Nixon on January 1, 1970. NEPA required federal agencies to prepare assessments and impact statements of proposed major projects and policy changes affecting the “human environment,” broadly defined to include both “the natural and physical environment and the relationship of people with that environment."1

 

NEPA would be the primary model for laws in states including New York, whose State Environmental Quality Review Act (SEQR) was enacted in 1975.  

 

Text Box: SEQR, like the federal law that inspired it, defines “environmental impacts” broadly, going well beyond actions affecting the natural ecology of air, water, flora and fauna.

While NEPA applies only to federal executive branch agencies, SEQR applies to the actions of state and local agencies in New York. In relatively rare cases where the two jurisdictions overlap, the respective reviews can be coordinated, so that the impact statement required by NEPA can be used to fulfill obligations under SEQR.2

 

It’s important to note that these laws were not designed as government’s primary line of defense against pollution—a purpose served by other statutes and regulations largely adopted after NEPA in the 1970s.3

 

NEPA’s overarching goals extend well beyond protecting the natural ecology of air, water, plants and animals to encompass the regulation of “aesthetic, historic, cultural, economic, social, or health [impacts], whether direct, indirect, or cumulative.”4 In similarly broad language, SEQR defines environmental factors to also include “noise, resources of agricultural, archeological, historic or aesthetic significance, existing patterns of population concentration, distribution or growth.”5

 

New York’s law goes a big step further by also regulating potential impacts on “existing community or neighborhood character”—an amorphous concept that, in some cases, has been construed broadly enough to block projects otherwise permissible under existing local land-use ordinances.6

 

NEPA and SEQR also differ in several other significant respects.

 

Federal courts have determined that NEPA mandates for federal agencies are “essentially procedural.”7 In other words, the law’s principal effect is to describe the process federal agencies must follow to implement a major new policy or project—but not to shape outcomes consistent with its lofty aims.8

 

New York’s SEQR, by contrast, can be used to force changes to “mitigate” environmental impacts—not only dictating how a project is built, but effectively deciding whether it gets built at all. Perhaps even more importantly, SEQR requires an Environmental Impact Statement (EIS) if the project “may” cause a significant adverse environmental impact, whereas NEPA effectively requires an EIS only if a proposed action will “significantly affect the quality of the human environment.”9 This further expands the scope of actions covered by the state law. And before a project can win final approval, SEQR requires that adverse environmental impacts be “minimized to the maximum extent practicable.”10

 

SEQR’s broader scope and its requirement for “maximum extent practicable” mitigation as a condition for potential approval make it more expansive and stringent than its federal counterpart, NEPA; indeed, as will be shown below, it is among the most expansive and stringent laws of its type in any state.

 

Where, When and How SEQR Applies

 

In addition to development projects, actions that may affect the “environment,” as broadly defined in the SEQR statute, include the adoption of new land-use laws, rules and regulations, bond financing resolutions for public projects and other required permits for private projects. In those instances, SEQR “requires the sponsoring or approving governmental body to identify and mitigate the significant environmental impacts of the activity it is proposing or permitting.”11 As further explained in the state’s SEQR Handbook:

 

In order for SEQR to be applied to any proposed action or related series of actions there must be at least one discretionary decision required by an agency. Often there are several such decisions necessary in order to carry out the action. For example, the “action” of developing a residential subdivision may require separate approval decisions by a town planning board for the subdivision plat, town board or zoning board of appeals if there is a zoning decision, or county health department if on-lot sewer and water facilities are required, and, possibly by the state Departments of Transportation or Environmental Conservation, if highway access or stream or other environmental permits are needed. No decision to approve, fund or directly undertake any part of an action should be made by any of these agencies until SEQR requirements are met. This SEQR review of an action may be done as part of a coordinated review process that involves several governmental agencies.12

 

Whether a specific project13 will actually be subject to SEQR depends on which of three categories it fits into: Type I, Type II, or Unlisted. Type I generally includes large projects involving significant changes that the law considers more likely to have significant “adverse” impacts on the environment.14 Sponsors of Type I actions must file a more detailed “full” version of an Environmental Assessment Form, or EAF.15  This form, in turn, is used by the lead agency as the basis for determining whether the project or proposal requires an EIS.

 

Type II includes smaller projects such as small subdivisions and additions to single-family homes, which are generally considered exempt from the law.16 Unlisted actions essentially consist of everything else.17 Sponsors of unlisted projects need to submit at least a “short” EAF.18

 

The SEQR process

 

When a proposal subject to SEQR requires decisions by more than one state or local agency, the law requires that a lead agency be designated to coordinate the SEQR review process, starting with a “significance of action determination” of whether the project may have any “significant adverse environmental impacts.”19 A “negative” or “conditional negative” declaration means the project has no significant adverse impacts or only involves impacts that will be avoided or minimized as much as possible, which effectively ends the SEQR process unless the circumstances change.

 

If the first stage of the process indicates the project may have significant adverse environmental impacts, the applicant must prepare a Draft Environmental Impact Statement (DEIS) fully describing the impacts along with any proposed mitigation measures.

 

The lead agency also may add a requirement for “scoping,” the goal of which is “to focus the EIS on potentially significant adverse impacts and to eliminate consideration of those impacts that are irrelevant or non-significant.”20 The scoping process must include an otherwise undefined and open-ended “period of time for the public to review and provide written comments on a draft scope or provide for public input through the use of meetings, exchanges of written material, or other means.”21

 

 

Once the lead agency is satisfied that the applicant’s DEIS describes a plan to sufficiently mitigate any significant adverse environmental impacts, the lead agency submits the draft for public comment, which can include a public hearing.22 After the lead agency adopts a Final Environmental Impact Statement (FEIS), it has 30 days to decide how to move forward with the underlying action—for example, issuance of a building permit.23

 

While the SEQR process does have some timelines, they don’t guarantee the process is completed within any particular time period. Most initial steps are given definitive time periods, including appointing a lead agency when multiple agencies are involved (30 calendar days), the significance of action determination (20 calendar days from receipt of application or all information received) and the optional “scoping” process (60 calendar day period for consideration of a draft scope). But while the agency is given up to 45 calendar days to consider a DEIS, or 30 days to consider a resubmitted DEIS, there is no limit on the amount of time it may take to approve it. 

 

Once a lead agency approves a draft impact statement, the clock starts ticking again on the SEQR process, starting with a minimum 30 calendar-day public comment period.24 Any additional public hearing must occur between 15 and 60 calendar days from the approval, with an additional 10 calendar days for comments afterward.25  The lead agency has 60 calendar days from the DEIS approval or 45 calendar days following the public hearing (whichever is later) to issue a final impact statement.26

 

 

2.      SEQR’S SELECT COMPANY

 

Thirty-seven states have adopted formal environmental review requirements based at least in part on the original federal NEPA statute, according to a 2009 assessment of such laws in the Journal of Environmental Planning and Management.27 In 21 of these states, however, environmental review provisions apply only to certain types of development activities, specific natural resource sectors, or particular geographic areas, the article indicates.28

 

New York is one of only 16 states with more broadly applicable, comprehensive environmental planning laws. These laws generally involve three steps: a determination of whether a proposed action is subject to review, an assessment of the environmental impact, and a detailed review of the action’s impacts and measures required to reduce or mitigate that impact.29

 

In addition to New York, states described as having comprehensive environmental planning statutes are California, Connecticut, Georgia, Hawaii, Indiana, Maryland, Massachusetts, Minnesota, Montana, New Jersey, North Carolina, South Dakota, Virginia, Washington, and Wisconsin.30

 

Some of those states adopted portions of the federal act almost verbatim.31 Others, the article said, imitate the federal law to varying degree. The most basic differences, (as shown in the table on page 6), include whether the statute applies to undertakings or approvals by local governments, how easy it is to trigger review, whether the statute has an action-forcing requirement, and whether it applies to private projects.

 

 

Even in this group, New York’s SEQR stands out among the most expansive and rigorous environmental planning laws in the nation.

 

Take, for instance, the issue of applicability. All 16 states with comprehensive laws require their state governments to conduct an environmental impact review in some circumstances. But New York is one of only eight states that apply this requirement to county or local government agency actions as well.32

 

Likewise, all 16 of the comprehensive environmental laws on the state level apply to development projects proposed or financially supported by state government.33 However, as shown below, only nine apply to private projects requiring other forms of government permission or approval—for example, zoning variance. In addition, only seven apply to proposed state and local policy changes, such as amendments to local zoning laws.34


 

New York’s state environmental review law is one of only three applying to every possible category of action in the article—policy changes as well as physical developments, local as well as state actions, private as well as public projects.35

 

As another basis of comparison, SEQR is one of 13 statewide review laws requiring preparation of an impact statement for a project or action that “may” significantly affect the environment. The remaining three, like the federal statute, require an impact statement only for projects or actions that will have such an effect.36 As noted above, NEPA’s impact is mainly procedural — and while the process it dictates still can entail substantial expenditures of time and money, the government agencies involved are not required to take an action based on its environmental impact review.

 

New York also is one of only six states whose environmental review laws include explicit “action-forcing” provisions, either requiring lead agencies or giving state agencies discretion to certify that adverse environmental impacts are either sufficiently mitigated or that reasonable alternatives are not available.37

 

In sum, New York’s SEQR is among a handful of comprehensive state environmental laws that are more widely applicable, more likely to impose a project change, and backed up by comprehensive regulatory structure.38 Most of the comparable state laws entail more limited applicability and largely procedural requirements, and thus appear “less dynamic in their relationship with state decision-making,” according to one leading environmental economist.39

 

 

 

3. JUDICIAL REVIEW OF SEQR

 

Unlike federal anti-pollution laws such as the Clean Water Act and Clean Air Act, NEPA did not include provisions allowing private citizens to file civil suits aimed at enforcing their provisions. Likewise, SEQR also does not contain a citizen suit or judicial review provision. The state Court of Appeals read this omission as reflecting the Legislature’s intention that “some limitation on standing to challenge administrative action was appropriate.”40

 

Challenges to the outcome of a SEQR process can be filed in state Supreme Court under Article 78 of the state Civil Practice Law and Rules, following the lead agency’s final determination or decision.41 Practically speaking, this means a SEQR challenge must commence at the very end of the process, after the lead agency has either approved a final impact statement or made a “negative” declaration (meaning no impact statement is required). All administrative remedies must be exhausted before an Article 78 proceeding can be initiated.42

 

This “ripeness” requirement usually thwarts challenges to interim agency actions. For instance, anyone challenging an agency for missing one of SEQR’s deadlines will find out that “these limitations essentially are unenforceable.”43 Even an agency’s positive declarations are not considered to be final determinations; therefore, with few exceptions, they have not been held subject to challenge.44

 

 

In addition, an Article 78 proceeding must commence within four months of the agency’s final determination —the only time period when an agency action is subject to challenge.45  Some cases suggest that shorter time periods are acceptable if a separate statute governing the agency determination has a shorter statute of limitations.46  There is also considerable disagreement over when the statute of limitations period begins, which further complicates matters.47

 

To challenge an agency under SEQR a person or organization must first have “standing,” which means they have a right to bring legal action under the statute. Traditionally, New York courts relied on the 1991 decision in The Society of the Plastics Industry, Inc. v. County of Suffolk.”48 Legal scholars note that some lower courts have “simplified and limited [this test] … into a requirement that a petitioner live in close proximity to the challenged project.”49

 

As long as the Plastics Industry standing test applied, New York was “effectively one of the most restrictive jurisdictions for environmental plaintiffs,” as one legal expert put it.50 More recently, in the case of Save the Pine Bush, Inc. v. Common Council of the City of Albany the state Court of Appeals held that individuals could have standing to challenge a government action involving a natural resource if they could demonstrate “repeated, not rare or isolated” recreational use of that natural resource.51

 

 

Although Pine Bush was perceived to broaden SEQR’s traditional standing requirements, recent appellate division cases suggest that these broader standards may only apply when the use of natural resources is at issue.52 When the circumstances do not involve use of a natural resource, some lower courts have continued to apply the more restrictive Plastics Industry standing test.53

 

For those with standing, Article 78 review is limited to whether the agency’s decision was an error of law, an abuse of discretion, or arbitrary and capricious.54 Courts interpreted this to mean they should “review the record to determine whether the agency identified the relevant areas of environmental concern, took a `hard look' at them, and made a ‘reasoned elaboration’ of the basis for its determination.”55

 

Courts in such cases have been deferential to lead agencies, holding that an FEIS does not need to consider every impact and every mitigation measure or alternative to satisfy SEQR.56 Consequently, they rarely disturb agency decisions when the challenge is to a FEIS. There were 55 court decisions on SEQR in 2012, including a dozen involving challenges to completed impact statements.57 In all 12 cases, the FEIS survived the challenge.58 Government agencies were overturned in seven of 34 cases that were challenged for lack of an original or supplemental EIS.59

 

By the same token, courts typically insist on strict compliance with the SEQR process and allow agencies little discretion as to the steps they must complete. However, some cases suggest that this standard might be loosening, given instances where courts allowed minor procedural irregularities as long as the public had full involvement in the process.60

 

 

While New York has relatively restrictive standing requirements and courts that typically defer to agency decision-making, SEQR-related lawsuits have been filed and decided at a fairly steady rate. Between 1975 and 2000, approximately 2,000 such cases were decided, including 700 between 1990 and 2000, or an annual average of 63.61  In the wake of the Great Recession, which began at the end of 2007, court rulings in SEQR cases declined to 45 cases in 2009, 37 cases in 2010, and 35 cases in 2011.62 In 2012, however, the number bounced back to 55.63

 

In sum, since the 1990s—despite the restrictions on standing and ripeness under Article 78—SEQR has given rise to enough litigation to generate an average of one court decision a year for each of the 57 counties outside New York City.

 

Statistics have not been kept on the number of SEQR-related lawsuits dismissed or withdrawn before trial—much less the number of development disputes in which a SEQR lawsuit is threatened. Nonetheless, the potential litigation related to SEQR can be as significant as any precedents generated by cases pursued through trial. 

 

As seen in the case of the Irondequoit Public Library (see box, page 10), the threat of a lawsuit can have a significant effect on the decision-making process. Although precedent and judicial deference likely would have supported Irondequoit’s initial determination, it still decided to spend $9,500 to complete a second full environmental assessment form.64 Such costs can be especially significant to small upstate municipalities.

 

<<NEXT PAGE>>

 


Endnotes:

140 C.F.R. §1508.14.
2“The SEQR Handbook: 3rd Edition – 2010,” Division of Environmental Permits, New York State Department of Environmental Conservation, pg. 188; available at: http://www.dec.ny.gov/docs/permits_ej_operations_pdf/seqrhandbook.pdf.
3Federal laws designed to protect the environment include the Clean Air Act (CAA), the Clean Water Act (CWA), the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA, or Superfund), the Endangered Species Act, the Oil Pollution Act, the Resource Recovery and Conservation Act, and the Safe Drinking Water Act, among others. Many of these laws have their counterparts on the state level or are enforced in part by the state DEC.
440 C.F.R. §1508.14.
5New York Environmental Conservation Law §8-0105(6).
6Ibid.

7Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U.S. 519, 558 (1978).
8Jeffrey Renz, “The Coming of Age of State Environmental Policy Acts,” 5 Pubic Land and Resources Law Review 31, pgs. 49-50 (1984)(“that by merely preparing, circulating and reviewing an EIS, an agency satisfies the acts’ requirements that the agency consider environmental im-pacts”).
942 U.S.C. §4332(c); see also: SEQR Handbook, NYSDEC at pg. 188.
10Environmental Conservation Law §8-0109(8); see also: 6 N.Y.C.R.R. §617.11(d)(5)(“[C]ertify that consistent with social, economic and other essential considerations from among the reasonable alternatives available, the action is one that avoids or minimizes adverse environmental impacts to the maximum extent practicable, and that adverse environmental impacts will be avoided or minimized to the maximum extent practicable by incorporating as conditions to the decisions those mitigative measures that were identified as practicable”).
11“SEQR: Environmental Impact Assessment in New York State,” New York State Department of Environmental Conservation website, (accessed 10/01/13), available at: http://www.dec.ny.gov/permits/357.html.
12“SEQR Handbook,” NYDEC, at pg. 14.
13The discussion throughout this paper focuses on specific projects and project-specific impact statements. However, less frequently, SEQR also can require a “generic” impact statement, or GEIS, “if a number of separate actions are proposed in a given geographic area and which, if considered singly, may have minor effects, but if considered together may have significant adverse environmental impacts; a sequence of related or contingent actions is planned by a single agency or individual; separate actions share common (generic) impacts; or a proposed program or plan would have wide application or restrict the range of future alternative policies or pro-jects,” SEQR Handbook, NYSDEC, at pgs. 99-100..
146 N.Y.C.R.R. §617.4
156 N.Y.C.R.R. §617.4(a)(2). There is both a ‘short’ form EAF and a ‘full’ form EAF, the full form is only required when the action/project is a defined as Type I (projects types likely to require an EIS). Any lead agency or project sponsor can choose to do a full form EAF.
166 N.Y.C.R.R. §617.5. Type II actions are excluded from SEQR review - examples include maintenance or repair involving no substantial damage to an existing structure or facility, repaving of existing highways, construction of commercial space less than 4,000 square feet that does not require a zoning change or variance, construction or expansion of single, two-family, and three-family homes on approved lots).
176 N.Y.C.R.R. §617.2(ak).
186 N.Y.C.R.R. §617.6(a)(3).
196 N.Y.C.R.R. §617.7. Agency can determine: “(1) To require an EIS for a proposed action, the lead agency must determine that the action may include the potential for at least one significant adverse environmental impact. (2) To determine that an EIS will not be required for an action, the lead agency must determine either that there will be no adverse environmental impacts or that the identified adverse environmental impacts will not be significant.” Note that this is different than the language in New York Environmental Conservation Law §8-0109. §8-0109 states that the agency shall prepare an EIS if the action “may have a significant effect on the environment.”
206 N.Y.C.R.R. §617.8(a).
216 N.Y.C.R.R. §617.8(e).
226 N.Y.C.R.R. §617.9.
236 N.Y.C.R.R. §617.11.
246 N.Y.C.R.R. §617.9(a)(3).
256 N.Y.C.R.R. §617.9(a)(4).
266 N.Y.C.R.R. §617.9(a)(5).
27Zhao Ma, Dennis R. Becker, and Michael A. Kilgore, “Characterising the landscape of state environmental review policies and procedures in the United States: a national assessment” Journal of Environmental Planning and Management, Vol. 52, No. 8, Pg. 1040 (Dec. 2009). States that have no formal environmental review requirements are: Alabama, Arizona, Colorado, Idaho, Iowa, New Hampshire, North Dakota, Ohio, Oklahoma, South Carolina, Tennessee, West Virginia, and Wyoming.
28Ibid at 1040. Including: Alaska, Arkansas, Delaware, Florida, Illinois, Kansas, Kentucky, Louisiana, Maine, Michigan, Mississippi, Missouri, Nebraska, Nevada, New Mexico, Oregon, Pennsylvania, Rhode Island, Texas, Utah, Vermont). See also: Rolf Pendall, “Problems and Prospects in Local Environmental Assessment: Lessons from the United States,” Journal of Environmental Planning and Management, 41(1) pgs. 5-23, (1998)(At least three of these 21 states—Texas, Utah, and New Mexico—initially adopted more widely applicable comprehensive envi-ronmental review laws in the 1970s but have since repealed them).
29Ma, Becker, and Kilgore, “Characterising the landscape of state environmental review policies and procedures in the United States: a national assessment,” at pg. 1039.
30Ibid at 1040; see also: “State NEPA Contacts,” The White House’s Council on Environmental Quality website; (accessed 1 Oct 2013), available at http://ceq.hss.doe.gov/state_information/States_NEPA_Like_22June2013.pdf.
31Indiana State Highway Commission v. Ziliak, 428 N.E.2d 275, 281 (1981 Ind. App.).
32The others are California, Georgia, Hawaii, Minnesota, New Jersey, North Carolina, and Washington.
33Ma, Becker, and Kilgore, “Characterising the landscape of state environmental review policies and procedures in the United States: a national assessment,” at pg. 1042.
34Ibid.
35Ma, Becker, and Kilgore, “Characterising the landscape of state environmental review policies and procedures in the United States: a national assessment,” at pg. 1042. The California Environ-mental Quality Act and Washington State Environmental Planning Act are the others.
36David Sive and Mark A. Chertok, ““Little NEPAs” and their Environmental Impact Assess-ment Procedures,” ALI-ABA: Environmental Litigation, pg. 9 (June 2005).
37While South Dakota’s statute has this action-forcing provision, the statute is applied only at the discretion of the agency reviewing the action. Thus, unlike the other states with this provision it is not a purely mandatory.
38Alan Gilpin, Environmental Impact Assessment: Cutting Edge for the 21st Century, Cambridge University Press, pg. 117-118 (1995).
39Ibid.
40The Society of the Plastics Industry, Inc. v. County of Suffolk, 77 N.Y.2d 761, 770 (1991)(stating that the Legislature intended to place some limitations on standing to challenge administrative action under SEQRA by failing to provide for citizen suits explicitly).
41N.Y. C.P.L.R. §7801.
42Rochester Telephone Mobile Communications v. Cole, 637 N.Y.S.2d 878 (4th Dep’t 1996).
43Michael B. Gerrard, “Judicial Review Under SEQRA: A Statistical Study,” 60 Albany Law Review 2, pg. 378; available at: http://www.albanylawreview.org/archives/65/2/JudicialReviewUnderSEQRA-AStatisticalStudy.pdf.
44Sour Mountain Realty v. N.Y. State Department of Environmental Conservation, 688 N.Y.S.2d 842, 845 (App. Div. 1999)(holding that a positive declaration is only a step and not a final determina-tion and that the case is not ripe for review).
45N.Y. C.P.L.R. §217.
46Haggerty v. Planning Board of Sand Lake, 166 A.D.2d 791, 792 (3d Dept. 1990)(holding that a thirty day statute of limitation contained in town law applied when town action was alleged to have violated SEQRA).
47Gordon v. Rush, 100 N.Y.2d 236 (2003)(holding that the statute of limitations started to run when the negative declaration was made); Stop-the-Barge v. Cahill, 771 N.Y.S.2d 40 (2003) (holding that the statute of limitations started to run when the positive declaration was made).
48The Society of the Plastics Industry, Inc. v. County of Suffolk, 77 N.Y.2d 761, 778 (1991).
49Mark A. Chertok and Ashley S. Miller, “Environmental Law: Developments in the Law of SEQRA,” 61 Syracuse L. Rev. 721, pg. 726, (2011); see also: Matter of Sun-Brite Car Wash v. Board of Zoning Appeals of Town of North Hempstead, 69 N.Y.2d 406 (1987); Save Our Main Street Buildings v. Greene County Legislature, 77 N.Y.2d 761 (1991).
50Gerrard, “Judicial Review Under SEQRA: A Statistical Study,” at pg. 372.
51Matter of Save the Pine Bush, Inc. v. Common Council of the City of Albany, 13 N.Y. 3d 297, 305 (2009); see also: Chertok and Miller, “Environmental Law: Developments in the Law of SEQRA,” at pg. 725.
52Peconic Baykeeper, Inc. v. Board of Trustees of the Freeholders & Commonalty of the Town of Southamp-ton, 2010 N.Y. Slip Op. 30182(U) (Sup. Ct. Suffolk County. 2010).
53Harris v. Town Board of Town of Riverhead, 905 N.Y.S.2d 598 (2d. Dep’t 2010)(holding that petitioners did not have standing to challenge a construction project where they did not live close enough to the state an injury on the basis of proximity alone and that traffic congestion and negative effects on business are not individual injuries that are different than the general public).
54Akpan v. Koch, 75 N.Y.2d 561, 570 (1990); see also: N.Y. C.P.L.R. §7803. The SEQRA challenge must be based on one of these four grounds: “1. whether the body or officer failed to perform a duty enjoined upon it by law; or 2. whether the body or officer proceeded, is proceeding or is about to proceed without or in excess of jurisdiction; or 3. whether a determination was made in violation of lawful procedure, was affected by an error of law or was arbitrary and capricious or an abuse of discretion, including abuse of discretion as to the measure or mode of penalty or discipline imposed; or 4. whether a determination made as a result of a hearing held, and at which evidence was taken, pursuant to direction by law is, on the entire record, supported by substantial evidence…”.
55Akpan at 570.
56Jackson v. New York State Urban Development Corporation, 67 N.Y.2d 400, 417 (1986).
57Michael B. Gerrard, “Survey of 2012 cases under State Environmental Quality Review Act,” 250 New York Law Journal 8 (11 July 2013).
58Ibid.
59Ibid.
60King v. Saratoga County Board of Supervisors, 675 N.E.2d 1185, 1188-9 (1996)(SEQRA requires strict compliance with procedural requirements and that anything less than strict compliance offers “the incentive to cut corners”); but see: Merson v. McNally 688 N.E.2d 479 (N.Y. 1997)(holding that an agency can determine a conditional negative declaration for a Type I action even though regulations seem to prohibit it, as long as the public is involved).
61Gerrard, “Judicial Review Under SEQRA: A Statistical Study,” at pg. 365 and 366.
62Michael B. Gerrard, “Recent Developments Under State Environmental Quality Review Act,” 248 New York Law Journal 8, pg. 1 (12 July 2012).
63Gerrard, “Survey of 2012 Cases Under State Environmental Quality Review Act,” at pg. 1.
64“Lawsuit could hold up Irondequoit library project; require new vote,” Irondequoit Post, 20 May 2013, at:
http://www.irondequoitpost.com/x90718543/Lawsuit-could-hold-up-Irondequoit-library-project-require-new-vote.